Key Issues and Future Directions for Addressing Challenges in Japan’s Offshore Wind Market

An Interim Compilation of Discussions from the

1st through 5th Bridging Forum Sessions

 

 

shihao-deng-iw_zwvajTHs-unsplash

Powering the Future Begins with Wind: From Ambition To Delivery In Japan’s Offshore Wind Market

Japan has set a target of 30-45 GW of offshore wind project formation by 2040, including 15 GW of floating offshore wind.

 

In Japan’s offshore wind framework, project formation is measured primarily by the implementation of public auctions.

 

Yet structural challenges — spanning both institutional and commercial dimensions — have emerged on the path to this target, as evidenced by the withdrawal of Round 1 awardees, delays to some Round 2 and 3 projects, and stalled auctions from Round 4 onward.

 

Through the Bridging Forum, a diverse range of stakeholders — policymakers, developers, supply chain companies, financial institutions, offtakers, and certification bodies — have engaged in open dialogue to develop a common understanding of these challenges.

 

10

風力が拓く未来:日本の洋上風力を、目標から確かな事業へ

日本は、2040年までに洋上風力発電を30〜45GW(うち浮体式15GW) の案件形成目標を掲げている。しかし、第1ラウンド採択事業者の撤退や 第2・第3ラウンドの一部案件の遅延、第4ラウンド以降の公募の停滞に象 徴されるように、目標達成に向けた制度面・事業面の構造的課題が顕在化 している。本Bridging Forumでは、これらの課題について、政策当局・開発 事業者・サプライチェーン企業・金融機関・需要家・認証機関等の多様なス テークホルダーが、率直な対話を通じて共通認識の形成を進めてきた。

 

Download The Report

 

Screenshot 2026-11-03 at 11.28.32

 

ダウンロードはこちら

Screenshot 2026-11-03 at 11.28.55
Miko Mendizabal

Media Inquiries

Miko Mendizabal

Regional Communications Specialist

  • ph_mail-bold

    Miko.Mendizabal@gwec.net