From the inception of the project to commissioning of the plant is usually 2-3 years or longer. However, most of the time is involved with planning, permitting, arranging financing, etc. The actual construction time is usually very short – a 10 MW wind farm can easily be built in two months. A larger 50 MW wind farm can be built in six months.